@@ -0,0 +1,170 @@
---
name: vm-migration
description: Migracao zero-downtime de workloads CWP e EasyPanel para VMs Proxmox com safety nets e rollback procedures.
layer: wiki
---
# VM Migration
Migracao zero-downtime de workloads CWP e EasyPanel para Proxmox VMs seguindo Migration-Plan-OptionA com safety nets e rollback procedures.
## Quando Usar
- Migrar servidores CWP para VMs Proxmox
- Migrar containers EasyPanel para VMs Proxmox
- Executar Migration-Plan-OptionA (3 fases)
- Migracao phased com validation periods
## Quando Nao Usar
- Migracoes non-CWP/EasyPanel (criar plan especifico)
- Ambientes teste/dev (menos rigor)
- Single-server setups (nao cluster)
## Sintaxe
```bash
/vm-migration <source-type> <source-host> [--phase 1|2|3] [--batch-size 5] [--validate-days 7]
```
## Exemplos
```bash
# Fase 1: EasyPanel migration (batch 5 containers)
/vm-migration easypanel easy.descomplicar.pt --phase 1 --batch-size 5
# Fase 2: CWP migration com 7 dias validation
/vm-migration cwp server.descomplicar.pt --phase 2 --validate-days 7
# Fase 3: Apenas confirmar (sem migracao)
/vm-migration finalize --phase 3
```
---
## Knowledge Sources (Consultar SEMPRE)
```bash
mcp__notebooklm__notebook_query \
notebook_id:"276ccdde-6b95-42a3-ad96-4e64d64c8d52" \
query:"proxmox migration cwp easypanel docker lxc zero downtime"
```
Hub Docs: `Hub/05-Projectos/Cluster Descomplicar/Planning/Migration-Plan-OptionA.md`
---
## Migration-Plan-OptionA Overview
**Timeline:** 8 semanas | **Strategy:** Phased migration com safety nets | **Rollback:** Disponivel em cada fase
```
Week 1-2: FASE 1 - EasyPanel Migration
+-- Backup EasyPanel -> PBS
+-- Create Docker VM Proxmox
+-- Migrate containers (batch 5-10)
+-- DNS cutover gradual
+-- Validation + Rollback window
Week 3-6: FASE 2 - CWP Migration
+-- 7 dias safety net (server intacto)
+-- Create AlmaLinux 8 VM
+-- Migrate CWP accounts (batch)
+-- Validate sites + email
+-- DNS cutover (TTL 300s)
+-- Rollback ate Day 7
Week 7-8: FASE 3 - Cluster Formation
+-- Prepare server.descomplicar.pt as Node A
+-- Form cluster (pvecm)
+-- Configure HA groups
+-- Live migration tests
+-- Cleanup legacy servers
```
---
## Workflow Pre-Migration (Todas Fases)
### 1. Backup Strategy Validation
```bash
# Verificar PBS configurado
pvesm status | grep pbs
# Criar backup point actual
vzdump --storage pbs-main --all 1 --mode snapshot
```
Garantir 3-2-1 compliance: original + PBS Node B + PBS Node A remote sync.
### 2. Documentar Estado Actual
```bash
# CWP: Listar contas
/scripts/list_accounts > /tmp/cwp-accounts.txt
# EasyPanel: Listar services
curl -s http://localhost:3000/api/trpc/projects.list | jq > /tmp/easypanel-services.json
# DNS TTLs (baixar para 300s ANTES de migration)
```
### 3. Comunicar Clientes (se downtime esperado)
- Email 48h antes
- Status page update
- Janela de manutencao agendada
---
## Fases Detalhadas
| Fase | Detalhes | Referencia |
|------|----------|------------|
| Fase 1: EasyPanel (Week 1-2) | 108 containers Docker -> VM Proxmox | [references/fase1-easypanel.md](references/fase1-easypanel.md) |
| Fase 2: CWP (Week 3-6) | 39 vhosts CWP -> VM AlmaLinux 8 | [references/fase2-cwp.md](references/fase2-cwp.md) |
| Fase 3: Cluster (Week 7-8) | 2-node cluster, HA, cleanup | [references/fase3-cluster.md](references/fase3-cluster.md) |
| Troubleshooting | Problemas comuns e resolucao | [references/troubleshooting.md](references/troubleshooting.md) |
---
## Backup Strategy Resumo
| Fase | Locais Backup | RPO | RTO |
|------|---------------|-----|-----|
| Fase 1 | Original + PBS + VPS | 1h | 2-4h |
| Fase 2 | Server intacto + PBS + /mnt/migration/ | 1h | 2-4h |
| Fase 3 | Node A + Node B + PBS dual | 1h | 2-4h |
---
## Anti-Patterns
| Anti-Pattern | Risco | Alternativa |
|--------------|-------|-------------|
| Migrar tudo de uma vez | Downtime total | Batches de 5-10 |
| Nao baixar TTL antes | DNS lento a propagar | TTL 300s 24h antes |
| Apagar server antigo cedo | Sem rollback | Manter 7 dias |
| Sem backup pre-migration | Perda dados | vzdump + 3-2-1 |
---
## References
- **Migration Plan:** Hub/05-Projectos/Cluster Descomplicar/Planning/Migration-Plan-OptionA.md
- **NotebookLM:** 276ccdde-6b95-42a3-ad96-4e64d64c8d52
- **Guia Hub:** Guia-Definitivo-Proxmox-Hetzner.md (Modulo 4: Workloads)
- **Desk CRM:** Projecto #65, Tarefa #1712
---
## Healing Log
Registo de erros conhecidos e como evitá-los. Lido automaticamente antes de executar.
```jsonl
{"date":"","issue":"","fix":"","source":"user|auto"}
```
*Adicionar nova linha após cada erro corrigido.*
@@ -0,0 +1,118 @@
# Fase 1: EasyPanel Migration (Week 1-2)
Target: Migrar 108 containers Docker para VM Proxmox
## 1.1 Criar VM Docker Host
```bash
qm create 200 \
--name easypanel-docker \
--memory 32768 \
--cores 8 \
--net0 virtio,bridge=vmbr0 \
--scsi0 rpool/vm-disks:200 \
--ostype l26 \
--boot order=scsi0
# Install Ubuntu 24.04 LTS
# Via Cloud-Init ou ISO manual
```
## 1.2 Instalar Docker + EasyPanel
```bash
ssh root@10.10.10.200
# Docker
curl -fsSL https://get.docker.com | sh
# EasyPanel
curl -sSL https://get.easypanel.io | sh
```
## 1.3 Backup Containers Actuais
```bash
# Em easy.descomplicar.pt
tar -czf /tmp/easypanel-volumes.tar.gz /var/lib/easypanel/projects
# Transfer para PBS ou storage temporario
scp /tmp/easypanel-volumes.tar.gz root@cluster.descomplicar.pt:/mnt/migration/
```
## 1.4 Migrar Containers (Batch 5-10)
Batch 1 (nao-criticos para teste):
```bash
# Containers teste: dev environments, staging
# IDs: 1-5
# Por cada container:
1. Exportar env vars do EasyPanel
2. Exportar docker-compose.yml
3. Copiar volumes
4. Recriar em novo EasyPanel
5. Testar health endpoint
6. DNS cutover se OK
```
Workflow Batch:
```bash
for container_id in 1 2 3 4 5; do
# Export config
curl -s http://easy.descomplicar.pt:3000/api/trpc/services.get \
-d "serviceId=$container_id" > config_$container_id.json
# Copiar volumes
rsync -avz /var/lib/easypanel/projects/$container_id/ \
root@10.10.10.200:/var/lib/easypanel/projects/$container_id/
# Recriar service (via EasyPanel API ou UI)
# Test
curl -I http://10.10.10.200:PORT/health
# DNS cutover (se health OK)
done
```
## 1.5 Validation (24-48h por batch)
```
Monitoring:
- Uptime checks (UptimeRobot ou similar)
- Error rates (logs)
- Performance (response time <500ms)
- Cliente feedback
Rollback triggers:
- >2 containers falham consecutivamente
- Cliente reporta down
- Health checks fail >10min
```
## 1.6 DNS Cutover
```bash
# Baixar TTL para 300s (5min) 24h ANTES
# Ex: Cloudflare ou dns.descomplicar.pt
# Cutover:
A record: old-ip -> NAT port forward para 10.10.10.200:PORT
# Monitorizar por 1h
# Reverter se problemas
```
## 1.7 Rollback Procedure
```bash
# Reverter DNS (TTL 300s = 5min propagacao)
# Reactivar container antigo
# Investigar causa falha
# Re-tentar apos fix
```
Batch 2-N: Repetir ate 108 containers migrados.
@@ -0,0 +1,112 @@
# Fase 2: CWP Migration (Week 3-6)
Target: Migrar 39 vhosts CWP para VM AlmaLinux 8
**CRITICAL:** 7 dias safety net - server.descomplicar.pt intacto
## 2.1 Criar VM AlmaLinux 8 + CWP
```bash
qm create 300 \
--name cwp-legacy \
--memory 16384 \
--cores 6 \
--net0 virtio,bridge=vmbr0 \
--scsi0 rpool/vm-disks:150 \
--ostype l26
# Instalar AlmaLinux 8
# Instalar CWP7
wget http://centos-webpanel.com/cwp-el8-latest
sh cwp-el8-latest
```
## 2.2 Backup CWP Accounts
```bash
# Em server.descomplicar.pt
for account in $(cat /tmp/cwp-accounts.txt); do
/scripts/pkgacct $account
done
# Transfer backups
rsync -avz /home/backup-*/cpmove-*.tar.gz \
root@cluster.descomplicar.pt:/mnt/migration/cwp/
```
## 2.3 Migrar Contas (Batch 3-5 contas)
Workflow por conta:
```bash
# 1. Restore backup em VM CWP
scp /mnt/migration/cwp/cpmove-ACCOUNT.tar.gz root@10.10.10.300:/home/
# 2. Restore via CWP
/scripts/restorepkg ACCOUNT
# 3. Validar:
- Site carrega (HTTP 200)
- Database conecta
- Email funciona (send test)
- SSL certificado valido
# 4. DNS cutover (TTL 300s)
A record: site.com -> 10.10.10.300 (via NAT port forward)
# 5. Monitorizar 24h
```
## 2.4 Validation Period (7 dias)
```bash
# Days 1-7 apos migration:
- Server antigo (server.descomplicar.pt) INTACTO
- Rollback instantaneo se problema critical
- Cliente pode reverter DNS manualmente se necessario
# Day 7: Confirmar com Emanuel
# Se tudo OK -> proceder cleanup
# Se problemas -> extend validation ou rollback completo
```
## 2.5 Email Migration
```bash
# Por cada conta CWP:
# 1. Backup mailboxes
tar -czf /tmp/mail-ACCOUNT.tar.gz /home/ACCOUNT/mail/
# 2. Transfer
scp /tmp/mail-ACCOUNT.tar.gz root@10.10.10.300:/tmp/
# 3. Restore
cd /home/ACCOUNT/
tar -xzf /tmp/mail-ACCOUNT.tar.gz
# 4. Fix permissions
chown -R ACCOUNT:ACCOUNT /home/ACCOUNT/mail/
# 5. Testar IMAP/SMTP
telnet localhost 143 # IMAP
telnet localhost 25 # SMTP
```
## 2.6 Rollback Procedure (Fase 2)
```bash
# Disponivel ate Day 7
# 1. Reverter DNS (todos sites)
A records -> IP antigo (server.descomplicar.pt)
# 2. Verificar server antigo online
ping server.descomplicar.pt
# 3. Comunicar clientes
# 4. Analisar causa falha
# 5. Ajustar plan e re-tentar
```
@@ -0,0 +1,63 @@
# Fase 3: Cluster Formation (Week 7-8)
Target: Formar cluster 2-node, HA, cleanup
## 3.1 Preparar server.descomplicar.pt como Node A
```bash
# APENAS apos Fase 2 100% validada
# Backup final completo
tar -czf /tmp/final-backup-server.tar.gz /etc /home /var/www
# Reformatar com Proxmox (/proxmox-setup)
# Tornar Node A do cluster
```
## 3.2 Cluster Formation
```bash
/proxmox-cluster create --node-a server.descomplicar.pt --node-b cluster.descomplicar.pt
```
## 3.3 HA Configuration
```bash
/proxmox-ha configure --critical-vms 200,300
```
## 3.4 Cleanup
```bash
# Cancelar easy.descomplicar.pt VPS (apos validacao)
# Backup final de tudo
# Documentar nova arquitectura
```
---
## Backup Strategy Durante Migration
### Fase 1 (EasyPanel)
3 locais:
1. Containers em easy.descomplicar.pt (original)
2. PBS Node B backup
3. easy.descomplicar.pt VPS backup (mantido durante Fase 1)
### Fase 2 (CWP)
Safety net 7 dias:
1. Server antigo intacto (rollback rapido)
2. VM CWP -> PBS backups automaticos
3. Backups manuais /mnt/migration/
RPO: 1h (PBS backups hourly se critical)
RTO: 2-4h (restore + DNS propagation)
### Fase 3 (Cluster)
Redundancia completa:
1. VMs em Node A + Node B
2. PBS primary (Node B 16TB)
3. PBS secondary remote sync (Node A 12TB)
@@ -0,0 +1,48 @@
# VM Migration - Troubleshooting
## Container migration fails
```bash
# Verificar logs
docker logs CONTAINER_ID
# Verificar volumes
ls -lah /var/lib/easypanel/projects/PROJECT/
# Testar manual
docker-compose up -d
# Rollback e investigar
```
## CWP site nao carrega apos migration
```bash
# Verificar Apache
systemctl status httpd
# Verificar vhost
cat /usr/local/apache/conf.d/vhosts/DOMAIN.conf
# Verificar database
mysql -u USER -p DATABASE
# Verificar DNS propagation
dig +short DOMAIN @8.8.8.8
```
## Email nao funciona
```bash
# Verificar Postfix
systemctl status postfix
# Testar SMTP
telnet localhost 25
# Verificar DNS MX
dig +short MX DOMAIN
# Verificar logs
tail -f /var/log/maillog
```