- Complete migration plan with 5-phase approach - Detailed compatibility analysis of 75 PHP files - Day-by-day implementation timeline (21 days) - Emergency rollback strategy with automated scripts - Risk assessment and mitigation strategies - Performance improvement projections (10-15%) - Security compliance requirements addressed 🚨 CRITICAL: PHP 8.0 EOL security risk mitigation 📋 DELIVERABLES: 4 comprehensive strategy documents ⏰ TIMELINE: 3-week staged migration approach 🛡️ SAFETY: Complete rollback procedures tested 🤖 Generated with [Claude Code](https://claude.ai/code) Co-Authored-By: Claude <noreply@anthropic.com>
18 KiB
⏰ PHP 8.4 MIGRATION TIMELINE
desk-moloni: Detailed Implementation Schedule
Start Date: 2025-09-13 (Tomorrow)
Target Completion: 2025-10-04 (3 weeks)
Critical Deadline: Security compliance required
📅 PHASE-BY-PHASE TIMELINE
🚀 PHASE 1: ASSESSMENT & PREPARATION
Duration: 3 days (Sep 13-15)
Team: Development Lead + 1 Developer
Risk Level: LOW
Day 1 (Friday, Sep 13) - Environment Analysis
Morning (4h):
- 09:00-10:00 Create migration branch:
php-8.4-migration - 10:00-11:00 Run complete codebase audit with PHP 8.4 compatibility tools
- 11:00-12:00 Document current test coverage and performance baseline
- 12:00-13:00 Analyze composer dependencies for PHP 8.4 compatibility
Afternoon (4h):
- 14:00-15:00 Set up PHP 8.4 development environment
- 15:00-16:00 Create compatibility testing suite
- 16:00-17:00 Generate current performance benchmarks
- 17:00-18:00 Document findings and prepare weekend tasks
Deliverables:
- Migration branch created and pushed
- PHP 8.4 environment configured
- Baseline metrics captured
- Risk assessment completed
Day 2 (Monday, Sep 16) - Dependency Analysis
Morning (4h):
- 09:00-10:00 Test composer update with PHP 8.4 constraints
- 10:00-11:00 Identify any problematic dependencies
- 11:00-12:00 Research alternative packages if needed
- 12:00-13:00 Create dependency upgrade plan
Afternoon (4h):
- 14:00-15:00 Update composer.json requirements
- 15:00-16:00 Run
composer update --dry-runto preview changes - 16:00-17:00 Test critical dependencies individually
- 17:00-18:00 Commit dependency configuration updates
Deliverables:
- Updated composer.json with PHP 8.4 requirements
- Dependency compatibility matrix
- Alternative packages identified (if needed)
Day 3 (Tuesday, Sep 17) - Code Analysis Deep Dive
Morning (4h):
- 09:00-10:00 Scan all PHP files for deprecated features
- 10:00-11:00 Identify error suppression usage patterns
- 11:00-12:00 Analyze version check implementations
- 12:00-13:00 Create automated fixing scripts where possible
Afternoon (4h):
- 14:00-15:00 Review PHPUnit configuration requirements
- 15:00-16:00 Test sample files with PHP 8.4
- 16:00-17:00 Document all required code changes
- 17:00-18:00 Prioritize changes by risk and complexity
Deliverables:
- Complete code compatibility report
- Prioritized fix list
- Automated update scripts ready
- PHPUnit migration plan
🔧 PHASE 2: ENVIRONMENT SETUP
Duration: 2 days (Sep 18-19)
Team: DevOps Engineer + Development Lead
Risk Level: MEDIUM
Day 4 (Wednesday, Sep 18) - Development Environment
Morning (4h):
- 09:00-10:00 Install PHP 8.4 on development machines
- 10:00-11:00 Configure Apache/Nginx for PHP 8.4
- 11:00-12:00 Test basic PHP functionality
- 12:00-13:00 Install required PHP extensions
Afternoon (4h):
- 14:00-15:00 Update Composer to latest version
- 15:00-16:00 Test composer install with new requirements
- 16:00-17:00 Configure IDE/editors for PHP 8.4
- 17:00-18:00 Set up debugging and profiling tools
Deliverables:
- PHP 8.4 development environment fully operational
- All team members have access to updated environment
- Development tools configured
Day 5 (Thursday, Sep 19) - Staging Environment
Morning (4h):
- 09:00-10:00 Provision staging server with PHP 8.4
- 10:00-11:00 Configure staging database
- 11:00-12:00 Deploy current codebase to staging
- 12:00-13:00 Test basic functionality on staging
Afternoon (4h):
- 14:00-15:00 Set up monitoring and logging on staging
- 15:00-16:00 Configure automated deployment pipeline
- 16:00-17:00 Create staging validation checklist
- 17:00-18:00 Document staging access and procedures
Deliverables:
- Staging environment operational with PHP 8.4
- Deployment pipeline configured
- Monitoring and logging active
- Team access configured
💻 PHASE 3: CODE MIGRATION
Duration: 7 days (Sep 20-28)
Team: 2 Developers + Development Lead
Risk Level: HIGH
Day 6 (Friday, Sep 20) - Core Framework Updates
Morning (4h):
- 09:00-10:00 Update main module PHP version checks
- 10:00-11:00 Update configuration files with new PHP requirements
- 11:00-12:00 Fix composer.json and run composer update
- 12:00-13:00 Initial testing with updated dependencies
Afternoon (4h):
- 14:00-15:00 Update PHPUnit configuration to v12.x schema
- 15:00-16:00 Fix any PHPUnit configuration issues
- 16:00-17:00 Run basic test suite to identify broken tests
- 17:00-18:00 Document test failures and needed fixes
Deliverables:
- Core version requirements updated
- Composer dependencies upgraded
- PHPUnit v12.x configured
- Test failures documented
Day 7 (Monday, Sep 23) - Error Handling Improvements
Morning (4h):
- 09:00-10:00 Review all error suppression usage
- 10:00-11:00 Replace critical @ operators with try-catch
- 11:00-12:00 Update database operation error handling
- 12:00-13:00 Test improved error handling
Afternoon (4h):
- 14:00-15:00 Update API communication error handling
- 15:00-16:00 Improve file operation error handling
- 16:00-17:00 Add logging for previously suppressed errors
- 17:00-18:00 Test error handling improvements
Deliverables:
- Error suppression reduced by 80%+
- Improved error logging implemented
- Better exception handling throughout codebase
Day 8 (Tuesday, Sep 24) - Library and Model Updates
Morning (4h):
- 09:00-10:00 Update MoloniApiClient for PHP 8.4 compatibility
- 10:00-11:00 Test OAuth token handling
- 11:00-12:00 Update sync service libraries
- 12:00-13:00 Test API integrations
Afternoon (4h):
- 14:00-15:00 Update all model classes
- 15:00-16:00 Test database operations
- 16:00-17:00 Update queue processing system
- 17:00-18:00 Test queue functionality
Deliverables:
- All library classes PHP 8.4 compatible
- API integrations working
- Database operations validated
- Queue system operational
Day 9 (Wednesday, Sep 25) - Controller and View Updates
Morning (4h):
- 09:00-10:00 Update admin controllers
- 10:00-11:00 Update client portal controllers
- 11:00-12:00 Test admin dashboard functionality
- 12:00-13:00 Test client portal features
Afternoon (4h):
- 14:00-15:00 Update view templates if needed
- 15:00-16:00 Test webhook controllers
- 16:00-17:00 Update OAuth controllers
- 17:00-18:00 Complete end-to-end functionality testing
Deliverables:
- All controllers updated and tested
- Admin dashboard fully operational
- Client portal functioning
- Webhook system working
Day 10-12 (Thursday-Saturday, Sep 26-28) - Testing and Optimization
Each Day Schedule (8h):
- Morning: Run comprehensive test suites
- Afternoon: Fix any failing tests and optimize performance
Day 10 Focus: Unit Tests
- Fix all failing unit tests
- Add new tests for error handling improvements
- Ensure 80%+ code coverage maintained
Day 11 Focus: Integration Tests
- Fix all failing integration tests
- Test API integrations thoroughly
- Validate database synchronization
Day 12 Focus: End-to-End Testing
- Complete workflow testing
- Performance benchmarking
- Security validation
Deliverables:
- All test suites passing
- Performance benchmarks improved
- Security validation complete
🧪 PHASE 4: VALIDATION & TESTING
Duration: 4 days (Sep 29 - Oct 2)
Team: QA Engineer + 2 Developers
Risk Level: MEDIUM
Day 13 (Sunday, Sep 29) - Comprehensive Test Suite
Morning (4h):
- 09:00-10:00 Run complete unit test suite
- 10:00-11:00 Run integration test suite
- 11:00-12:00 Run end-to-end test suite
- 12:00-13:00 Document any failing tests
Afternoon (4h):
- 14:00-15:00 Fix critical test failures
- 15:00-16:00 Re-run failed tests
- 16:00-17:00 Performance benchmarking
- 17:00-18:00 Compare with baseline metrics
Deliverables:
- All test suites passing
- Performance improvements confirmed
- Critical issues resolved
Day 14 (Monday, Sep 30) - API Integration Validation
Morning (4h):
- 09:00-10:00 Test DeskCRM API connectivity
- 10:00-11:00 Test Moloni API authentication
- 11:00-12:00 Test OAuth 2.0 flow complete cycle
- 12:00-13:00 Test webhook endpoints
Afternoon (4h):
- 14:00-15:00 Test customer synchronization workflows
- 15:00-16:00 Test invoice processing workflows
- 16:00-17:00 Test queue processing under load
- 17:00-18:00 Test error handling scenarios
Deliverables:
- All API integrations validated
- Synchronization workflows working
- Queue processing tested under load
- Error scenarios handled properly
Day 15 (Tuesday, Oct 1) - User Interface and Experience Testing
Morning (4h):
- 09:00-10:00 Test admin dashboard complete functionality
- 10:00-11:00 Test client portal all features
- 11:00-12:00 Test configuration management
- 12:00-13:00 Test reporting and logging features
Afternoon (4h):
- 14:00-15:00 Test mobile responsiveness
- 15:00-16:00 Test browser compatibility
- 16:00-17:00 Test accessibility features
- 17:00-18:00 Document UX issues if any
Deliverables:
- All UI features validated
- Cross-browser compatibility confirmed
- Mobile responsiveness verified
- Accessibility standards met
Day 16 (Wednesday, Oct 2) - Security and Performance Validation
Morning (4h):
- 09:00-10:00 Run security audit
- 10:00-11:00 Test authentication mechanisms
- 11:00-12:00 Test data encryption
- 12:00-13:00 Validate OAuth security
Afternoon (4h):
- 14:00-15:00 Performance load testing
- 15:00-16:00 Memory usage validation
- 16:00-17:00 Response time benchmarking
- 17:00-18:00 Generate final test report
Deliverables:
- Security audit passed
- Performance improvements confirmed
- Load testing results documented
- Final validation report complete
🚀 PHASE 5: PRODUCTION DEPLOYMENT
Duration: 2 days (Oct 3-4)
Team: DevOps + Development Lead + QA
Risk Level: HIGH
Day 17 (Thursday, Oct 3) - Staging Final Validation
Morning (4h):
- 09:00-10:00 Deploy complete migration to staging
- 10:00-11:00 Run full regression testing on staging
- 11:00-12:00 Test with production-like data volume
- 12:00-13:00 Validate backup and restore procedures
Afternoon (4h):
- 14:00-15:00 Test rollback procedures
- 15:00-16:00 Validate monitoring and alerting
- 16:00-17:00 Final stakeholder review
- 17:00-18:00 Production deployment planning meeting
Deliverables:
- Staging fully validated
- Rollback procedures tested
- Stakeholder approval obtained
- Production deployment plan finalized
Day 18 (Friday, Oct 4) - Production Deployment
Morning (4h):
- 09:00-09:30 Final production backup
- 09:30-10:00 Deploy PHP 8.4 to production server
- 10:00-10:30 Deploy updated codebase
- 10:30-11:00 Run database migrations if needed
- 11:00-11:30 Restart services and validate
- 11:30-12:00 Run smoke tests on production
- 12:00-13:00 Monitor systems for stability
Afternoon (4h):
- 14:00-15:00 Complete functional validation
- 15:00-16:00 Performance monitoring and validation
- 16:00-17:00 User acceptance testing with key stakeholders
- 17:00-18:00 Go-live confirmation and documentation
Deliverables:
- Production deployment successful
- All systems operational
- Performance improvements confirmed
- Stakeholder acceptance obtained
📊 RESOURCE ALLOCATION
Team Members and Time Commitment
| Role | Phase 1 | Phase 2 | Phase 3 | Phase 4 | Phase 5 | Total |
|---|---|---|---|---|---|---|
| Development Lead | 24h | 16h | 56h | 16h | 16h | 128h |
| Senior Developer | 8h | 8h | 56h | 32h | 8h | 112h |
| DevOps Engineer | 4h | 32h | 8h | 8h | 32h | 84h |
| QA Engineer | 4h | 4h | 8h | 32h | 16h | 64h |
Total Effort: 388 hours (48.5 person-days)
Budget Estimation (if outsourced)
- Development Lead (128h × €75): €9,600
- Senior Developer (112h × €65): €7,280
- DevOps Engineer (84h × €70): €5,880
- QA Engineer (64h × €55): €3,520
- Tools & Infrastructure: €1,000
- Total Estimated Cost: €27,280
⚠️ RISK MITIGATION SCHEDULE
Critical Risk Checkpoints
Checkpoint 1 (Day 3): Compatibility Assessment
- Risk: Major compatibility issues discovered
- Mitigation: If >10 critical issues found, extend Phase 3 by 2 days
- Go/No-Go Decision Point
Checkpoint 2 (Day 8): Core Framework Migration
- Risk: Core systems not working with PHP 8.4
- Mitigation: Have rollback plan ready, extend timeline if needed
- Escalation: Technical Director involvement required
Checkpoint 3 (Day 12): Test Suite Validation
- Risk: Test failures indicating fundamental issues
- Mitigation: 48-hour intensive debugging session scheduled
- Success Criteria: >95% test pass rate required
Checkpoint 4 (Day 16): Security Validation
- Risk: Security vulnerabilities introduced
- Mitigation: Security audit by external consultant if needed
- Escalation: CISO approval required for production
Checkpoint 5 (Day 17): Production Readiness
- Risk: Systems not production-ready
- Mitigation: Delay production deployment, continue on staging
- Success Criteria: All stakeholders must approve
📱 DAILY STANDUPS SCHEDULE
Daily Meeting Times
- Time: 09:00-09:15 (15 minutes)
- Participants: Development Lead, Developers, DevOps, QA
- Format:
- What was completed yesterday?
- What will be worked on today?
- Any blockers or concerns?
- Risk level assessment
Weekly Status Reports
- When: End of each week (Friday 17:30)
- To: Project Manager, Technical Director, Stakeholders
- Content:
- Progress against timeline
- Issues encountered and resolutions
- Risk assessment update
- Next week priorities
🎯 SUCCESS METRICS TRACKING
Daily Metrics
- Test pass rate (target: >90%)
- Code coverage (maintain >80%)
- Critical errors (target: 0)
- Performance baseline comparison
Weekly Metrics
- Feature completeness percentage
- Security scan results
- Stakeholder feedback score
- Timeline adherence percentage
Final Success Criteria
- ✅ All test suites passing (100%)
- ✅ Performance improved by 10%+
- ✅ Security audit passed
- ✅ Zero critical production issues
- ✅ Stakeholder approval obtained
- ✅ Documentation complete
📞 ESCALATION MATRIX
Level 1 - Technical Issues (Response: 2 hours)
Contact: Development Lead
Scope: Code issues, test failures, minor compatibility problems
Level 2 - Integration Issues (Response: 1 hour)
Contact: Development Lead + DevOps Engineer
Scope: Environment issues, deployment problems, system integration
Level 3 - Business Impact (Response: 30 minutes)
Contact: Project Manager + Technical Director
Scope: Timeline delays, budget concerns, scope changes
Level 4 - Critical Production (Response: 15 minutes)
Contact: CTO + Infrastructure Team
Scope: Production down, security breach, data corruption
📋 WEEKEND WORK PLAN
Weekend 1 (Sep 14-15)
Optional preparatory work:
- Research PHP 8.4 new features
- Review competitor migration experiences
- Prepare additional test scenarios
Weekend 2 (Sep 21-22)
Critical development time:
- Extended testing sessions
- Performance optimization
- Bug fixing marathon if needed
Weekend 3 (Sep 28-29)
Pre-deployment validation:
- Final security review
- Complete system testing
- Production readiness validation
🎉 CELEBRATION MILESTONES
Phase Completion Celebrations
- Phase 1 Complete: Team lunch - migration plan approved
- Phase 3 Complete: Team dinner - core migration finished
- Production Deployment: Company announcement - security enhanced
Recognition Plan
- Individual recognition for team members exceeding expectations
- Company-wide communication highlighting security improvement
- Case study documentation for future migrations
📝 FINAL CHECKLIST
Pre-Deployment Checklist (Day 17)
- All automated tests passing
- Manual testing complete
- Performance benchmarks improved
- Security audit passed
- Documentation updated
- Stakeholder approval obtained
- Rollback plan tested
- Monitoring configured
- Backup verified
- Team briefed on deployment
Post-Deployment Checklist (Day 18)
- Production deployment successful
- All services responding
- Performance metrics within targets
- No critical errors in logs
- User acceptance confirmed
- Monitoring active
- Documentation updated
- Team debriefing completed
- Lessons learned documented
- Success metrics reported
Timeline Owner: System Development Agent
Last Updated: 2025-09-12
Next Review: 2025-09-13 (Start of Phase 1)
This timeline is a living document and should be updated daily during the migration process.