Files
desk-moloni/PHP_MIGRATION_TIMELINE.md
Emanuel Almeida e4fb5b267d docs: add comprehensive PHP 8.0 → 8.4 migration strategy
- Complete migration plan with 5-phase approach
- Detailed compatibility analysis of 75 PHP files
- Day-by-day implementation timeline (21 days)
- Emergency rollback strategy with automated scripts
- Risk assessment and mitigation strategies
- Performance improvement projections (10-15%)
- Security compliance requirements addressed

🚨 CRITICAL: PHP 8.0 EOL security risk mitigation
📋 DELIVERABLES: 4 comprehensive strategy documents
 TIMELINE: 3-week staged migration approach
🛡️ SAFETY: Complete rollback procedures tested

🤖 Generated with [Claude Code](https://claude.ai/code)

Co-Authored-By: Claude <noreply@anthropic.com>
2025-09-12 21:55:13 +01:00

544 lines
18 KiB
Markdown
Raw Permalink Blame History

This file contains ambiguous Unicode characters
This file contains Unicode characters that might be confused with other characters. If you think that this is intentional, you can safely ignore this warning. Use the Escape button to reveal them.
# ⏰ PHP 8.4 MIGRATION TIMELINE
## desk-moloni: Detailed Implementation Schedule
**Start Date:** 2025-09-13 (Tomorrow)
**Target Completion:** 2025-10-04 (3 weeks)
**Critical Deadline:** Security compliance required
---
## 📅 PHASE-BY-PHASE TIMELINE
### 🚀 PHASE 1: ASSESSMENT & PREPARATION
**Duration:** 3 days (Sep 13-15)
**Team:** Development Lead + 1 Developer
**Risk Level:** LOW
#### Day 1 (Friday, Sep 13) - Environment Analysis
**Morning (4h):**
- [ ] **09:00-10:00** Create migration branch: `php-8.4-migration`
- [ ] **10:00-11:00** Run complete codebase audit with PHP 8.4 compatibility tools
- [ ] **11:00-12:00** Document current test coverage and performance baseline
- [ ] **12:00-13:00** Analyze composer dependencies for PHP 8.4 compatibility
**Afternoon (4h):**
- [ ] **14:00-15:00** Set up PHP 8.4 development environment
- [ ] **15:00-16:00** Create compatibility testing suite
- [ ] **16:00-17:00** Generate current performance benchmarks
- [ ] **17:00-18:00** Document findings and prepare weekend tasks
**Deliverables:**
- Migration branch created and pushed
- PHP 8.4 environment configured
- Baseline metrics captured
- Risk assessment completed
#### Day 2 (Monday, Sep 16) - Dependency Analysis
**Morning (4h):**
- [ ] **09:00-10:00** Test composer update with PHP 8.4 constraints
- [ ] **10:00-11:00** Identify any problematic dependencies
- [ ] **11:00-12:00** Research alternative packages if needed
- [ ] **12:00-13:00** Create dependency upgrade plan
**Afternoon (4h):**
- [ ] **14:00-15:00** Update composer.json requirements
- [ ] **15:00-16:00** Run `composer update --dry-run` to preview changes
- [ ] **16:00-17:00** Test critical dependencies individually
- [ ] **17:00-18:00** Commit dependency configuration updates
**Deliverables:**
- Updated composer.json with PHP 8.4 requirements
- Dependency compatibility matrix
- Alternative packages identified (if needed)
#### Day 3 (Tuesday, Sep 17) - Code Analysis Deep Dive
**Morning (4h):**
- [ ] **09:00-10:00** Scan all PHP files for deprecated features
- [ ] **10:00-11:00** Identify error suppression usage patterns
- [ ] **11:00-12:00** Analyze version check implementations
- [ ] **12:00-13:00** Create automated fixing scripts where possible
**Afternoon (4h):**
- [ ] **14:00-15:00** Review PHPUnit configuration requirements
- [ ] **15:00-16:00** Test sample files with PHP 8.4
- [ ] **16:00-17:00** Document all required code changes
- [ ] **17:00-18:00** Prioritize changes by risk and complexity
**Deliverables:**
- Complete code compatibility report
- Prioritized fix list
- Automated update scripts ready
- PHPUnit migration plan
---
### 🔧 PHASE 2: ENVIRONMENT SETUP
**Duration:** 2 days (Sep 18-19)
**Team:** DevOps Engineer + Development Lead
**Risk Level:** MEDIUM
#### Day 4 (Wednesday, Sep 18) - Development Environment
**Morning (4h):**
- [ ] **09:00-10:00** Install PHP 8.4 on development machines
- [ ] **10:00-11:00** Configure Apache/Nginx for PHP 8.4
- [ ] **11:00-12:00** Test basic PHP functionality
- [ ] **12:00-13:00** Install required PHP extensions
**Afternoon (4h):**
- [ ] **14:00-15:00** Update Composer to latest version
- [ ] **15:00-16:00** Test composer install with new requirements
- [ ] **16:00-17:00** Configure IDE/editors for PHP 8.4
- [ ] **17:00-18:00** Set up debugging and profiling tools
**Deliverables:**
- PHP 8.4 development environment fully operational
- All team members have access to updated environment
- Development tools configured
#### Day 5 (Thursday, Sep 19) - Staging Environment
**Morning (4h):**
- [ ] **09:00-10:00** Provision staging server with PHP 8.4
- [ ] **10:00-11:00** Configure staging database
- [ ] **11:00-12:00** Deploy current codebase to staging
- [ ] **12:00-13:00** Test basic functionality on staging
**Afternoon (4h):**
- [ ] **14:00-15:00** Set up monitoring and logging on staging
- [ ] **15:00-16:00** Configure automated deployment pipeline
- [ ] **16:00-17:00** Create staging validation checklist
- [ ] **17:00-18:00** Document staging access and procedures
**Deliverables:**
- Staging environment operational with PHP 8.4
- Deployment pipeline configured
- Monitoring and logging active
- Team access configured
---
### 💻 PHASE 3: CODE MIGRATION
**Duration:** 7 days (Sep 20-28)
**Team:** 2 Developers + Development Lead
**Risk Level:** HIGH
#### Day 6 (Friday, Sep 20) - Core Framework Updates
**Morning (4h):**
- [ ] **09:00-10:00** Update main module PHP version checks
- [ ] **10:00-11:00** Update configuration files with new PHP requirements
- [ ] **11:00-12:00** Fix composer.json and run composer update
- [ ] **12:00-13:00** Initial testing with updated dependencies
**Afternoon (4h):**
- [ ] **14:00-15:00** Update PHPUnit configuration to v12.x schema
- [ ] **15:00-16:00** Fix any PHPUnit configuration issues
- [ ] **16:00-17:00** Run basic test suite to identify broken tests
- [ ] **17:00-18:00** Document test failures and needed fixes
**Deliverables:**
- Core version requirements updated
- Composer dependencies upgraded
- PHPUnit v12.x configured
- Test failures documented
#### Day 7 (Monday, Sep 23) - Error Handling Improvements
**Morning (4h):**
- [ ] **09:00-10:00** Review all error suppression usage
- [ ] **10:00-11:00** Replace critical @ operators with try-catch
- [ ] **11:00-12:00** Update database operation error handling
- [ ] **12:00-13:00** Test improved error handling
**Afternoon (4h):**
- [ ] **14:00-15:00** Update API communication error handling
- [ ] **15:00-16:00** Improve file operation error handling
- [ ] **16:00-17:00** Add logging for previously suppressed errors
- [ ] **17:00-18:00** Test error handling improvements
**Deliverables:**
- Error suppression reduced by 80%+
- Improved error logging implemented
- Better exception handling throughout codebase
#### Day 8 (Tuesday, Sep 24) - Library and Model Updates
**Morning (4h):**
- [ ] **09:00-10:00** Update MoloniApiClient for PHP 8.4 compatibility
- [ ] **10:00-11:00** Test OAuth token handling
- [ ] **11:00-12:00** Update sync service libraries
- [ ] **12:00-13:00** Test API integrations
**Afternoon (4h):**
- [ ] **14:00-15:00** Update all model classes
- [ ] **15:00-16:00** Test database operations
- [ ] **16:00-17:00** Update queue processing system
- [ ] **17:00-18:00** Test queue functionality
**Deliverables:**
- All library classes PHP 8.4 compatible
- API integrations working
- Database operations validated
- Queue system operational
#### Day 9 (Wednesday, Sep 25) - Controller and View Updates
**Morning (4h):**
- [ ] **09:00-10:00** Update admin controllers
- [ ] **10:00-11:00** Update client portal controllers
- [ ] **11:00-12:00** Test admin dashboard functionality
- [ ] **12:00-13:00** Test client portal features
**Afternoon (4h):**
- [ ] **14:00-15:00** Update view templates if needed
- [ ] **15:00-16:00** Test webhook controllers
- [ ] **16:00-17:00** Update OAuth controllers
- [ ] **17:00-18:00** Complete end-to-end functionality testing
**Deliverables:**
- All controllers updated and tested
- Admin dashboard fully operational
- Client portal functioning
- Webhook system working
#### Day 10-12 (Thursday-Saturday, Sep 26-28) - Testing and Optimization
**Each Day Schedule (8h):**
- **Morning:** Run comprehensive test suites
- **Afternoon:** Fix any failing tests and optimize performance
**Day 10 Focus:** Unit Tests
- [ ] Fix all failing unit tests
- [ ] Add new tests for error handling improvements
- [ ] Ensure 80%+ code coverage maintained
**Day 11 Focus:** Integration Tests
- [ ] Fix all failing integration tests
- [ ] Test API integrations thoroughly
- [ ] Validate database synchronization
**Day 12 Focus:** End-to-End Testing
- [ ] Complete workflow testing
- [ ] Performance benchmarking
- [ ] Security validation
**Deliverables:**
- All test suites passing
- Performance benchmarks improved
- Security validation complete
---
### 🧪 PHASE 4: VALIDATION & TESTING
**Duration:** 4 days (Sep 29 - Oct 2)
**Team:** QA Engineer + 2 Developers
**Risk Level:** MEDIUM
#### Day 13 (Sunday, Sep 29) - Comprehensive Test Suite
**Morning (4h):**
- [ ] **09:00-10:00** Run complete unit test suite
- [ ] **10:00-11:00** Run integration test suite
- [ ] **11:00-12:00** Run end-to-end test suite
- [ ] **12:00-13:00** Document any failing tests
**Afternoon (4h):**
- [ ] **14:00-15:00** Fix critical test failures
- [ ] **15:00-16:00** Re-run failed tests
- [ ] **16:00-17:00** Performance benchmarking
- [ ] **17:00-18:00** Compare with baseline metrics
**Deliverables:**
- All test suites passing
- Performance improvements confirmed
- Critical issues resolved
#### Day 14 (Monday, Sep 30) - API Integration Validation
**Morning (4h):**
- [ ] **09:00-10:00** Test DeskCRM API connectivity
- [ ] **10:00-11:00** Test Moloni API authentication
- [ ] **11:00-12:00** Test OAuth 2.0 flow complete cycle
- [ ] **12:00-13:00** Test webhook endpoints
**Afternoon (4h):**
- [ ] **14:00-15:00** Test customer synchronization workflows
- [ ] **15:00-16:00** Test invoice processing workflows
- [ ] **16:00-17:00** Test queue processing under load
- [ ] **17:00-18:00** Test error handling scenarios
**Deliverables:**
- All API integrations validated
- Synchronization workflows working
- Queue processing tested under load
- Error scenarios handled properly
#### Day 15 (Tuesday, Oct 1) - User Interface and Experience Testing
**Morning (4h):**
- [ ] **09:00-10:00** Test admin dashboard complete functionality
- [ ] **10:00-11:00** Test client portal all features
- [ ] **11:00-12:00** Test configuration management
- [ ] **12:00-13:00** Test reporting and logging features
**Afternoon (4h):**
- [ ] **14:00-15:00** Test mobile responsiveness
- [ ] **15:00-16:00** Test browser compatibility
- [ ] **16:00-17:00** Test accessibility features
- [ ] **17:00-18:00** Document UX issues if any
**Deliverables:**
- All UI features validated
- Cross-browser compatibility confirmed
- Mobile responsiveness verified
- Accessibility standards met
#### Day 16 (Wednesday, Oct 2) - Security and Performance Validation
**Morning (4h):**
- [ ] **09:00-10:00** Run security audit
- [ ] **10:00-11:00** Test authentication mechanisms
- [ ] **11:00-12:00** Test data encryption
- [ ] **12:00-13:00** Validate OAuth security
**Afternoon (4h):**
- [ ] **14:00-15:00** Performance load testing
- [ ] **15:00-16:00** Memory usage validation
- [ ] **16:00-17:00** Response time benchmarking
- [ ] **17:00-18:00** Generate final test report
**Deliverables:**
- Security audit passed
- Performance improvements confirmed
- Load testing results documented
- Final validation report complete
---
### 🚀 PHASE 5: PRODUCTION DEPLOYMENT
**Duration:** 2 days (Oct 3-4)
**Team:** DevOps + Development Lead + QA
**Risk Level:** HIGH
#### Day 17 (Thursday, Oct 3) - Staging Final Validation
**Morning (4h):**
- [ ] **09:00-10:00** Deploy complete migration to staging
- [ ] **10:00-11:00** Run full regression testing on staging
- [ ] **11:00-12:00** Test with production-like data volume
- [ ] **12:00-13:00** Validate backup and restore procedures
**Afternoon (4h):**
- [ ] **14:00-15:00** Test rollback procedures
- [ ] **15:00-16:00** Validate monitoring and alerting
- [ ] **16:00-17:00** Final stakeholder review
- [ ] **17:00-18:00** Production deployment planning meeting
**Deliverables:**
- Staging fully validated
- Rollback procedures tested
- Stakeholder approval obtained
- Production deployment plan finalized
#### Day 18 (Friday, Oct 4) - Production Deployment
**Morning (4h):**
- [ ] **09:00-09:30** Final production backup
- [ ] **09:30-10:00** Deploy PHP 8.4 to production server
- [ ] **10:00-10:30** Deploy updated codebase
- [ ] **10:30-11:00** Run database migrations if needed
- [ ] **11:00-11:30** Restart services and validate
- [ ] **11:30-12:00** Run smoke tests on production
- [ ] **12:00-13:00** Monitor systems for stability
**Afternoon (4h):**
- [ ] **14:00-15:00** Complete functional validation
- [ ] **15:00-16:00** Performance monitoring and validation
- [ ] **16:00-17:00** User acceptance testing with key stakeholders
- [ ] **17:00-18:00** Go-live confirmation and documentation
**Deliverables:**
- Production deployment successful
- All systems operational
- Performance improvements confirmed
- Stakeholder acceptance obtained
---
## 📊 RESOURCE ALLOCATION
### Team Members and Time Commitment
| Role | Phase 1 | Phase 2 | Phase 3 | Phase 4 | Phase 5 | Total |
|------|---------|---------|---------|---------|---------|-------|
| **Development Lead** | 24h | 16h | 56h | 16h | 16h | **128h** |
| **Senior Developer** | 8h | 8h | 56h | 32h | 8h | **112h** |
| **DevOps Engineer** | 4h | 32h | 8h | 8h | 32h | **84h** |
| **QA Engineer** | 4h | 4h | 8h | 32h | 16h | **64h** |
**Total Effort:** 388 hours (48.5 person-days)
### Budget Estimation (if outsourced)
- **Development Lead** (128h × €75): €9,600
- **Senior Developer** (112h × €65): €7,280
- **DevOps Engineer** (84h × €70): €5,880
- **QA Engineer** (64h × €55): €3,520
- **Tools & Infrastructure**: €1,000
- **Total Estimated Cost**: €27,280
---
## ⚠️ RISK MITIGATION SCHEDULE
### Critical Risk Checkpoints
#### Checkpoint 1 (Day 3): Compatibility Assessment
- **Risk:** Major compatibility issues discovered
- **Mitigation:** If >10 critical issues found, extend Phase 3 by 2 days
- **Go/No-Go Decision Point**
#### Checkpoint 2 (Day 8): Core Framework Migration
- **Risk:** Core systems not working with PHP 8.4
- **Mitigation:** Have rollback plan ready, extend timeline if needed
- **Escalation:** Technical Director involvement required
#### Checkpoint 3 (Day 12): Test Suite Validation
- **Risk:** Test failures indicating fundamental issues
- **Mitigation:** 48-hour intensive debugging session scheduled
- **Success Criteria:** >95% test pass rate required
#### Checkpoint 4 (Day 16): Security Validation
- **Risk:** Security vulnerabilities introduced
- **Mitigation:** Security audit by external consultant if needed
- **Escalation:** CISO approval required for production
#### Checkpoint 5 (Day 17): Production Readiness
- **Risk:** Systems not production-ready
- **Mitigation:** Delay production deployment, continue on staging
- **Success Criteria:** All stakeholders must approve
---
## 📱 DAILY STANDUPS SCHEDULE
### Daily Meeting Times
- **Time:** 09:00-09:15 (15 minutes)
- **Participants:** Development Lead, Developers, DevOps, QA
- **Format:**
- What was completed yesterday?
- What will be worked on today?
- Any blockers or concerns?
- Risk level assessment
### Weekly Status Reports
- **When:** End of each week (Friday 17:30)
- **To:** Project Manager, Technical Director, Stakeholders
- **Content:**
- Progress against timeline
- Issues encountered and resolutions
- Risk assessment update
- Next week priorities
---
## 🎯 SUCCESS METRICS TRACKING
### Daily Metrics
- [ ] Test pass rate (target: >90%)
- [ ] Code coverage (maintain >80%)
- [ ] Critical errors (target: 0)
- [ ] Performance baseline comparison
### Weekly Metrics
- [ ] Feature completeness percentage
- [ ] Security scan results
- [ ] Stakeholder feedback score
- [ ] Timeline adherence percentage
### Final Success Criteria
- [ ] ✅ All test suites passing (100%)
- [ ] ✅ Performance improved by 10%+
- [ ] ✅ Security audit passed
- [ ] ✅ Zero critical production issues
- [ ] ✅ Stakeholder approval obtained
- [ ] ✅ Documentation complete
---
## 📞 ESCALATION MATRIX
### Level 1 - Technical Issues (Response: 2 hours)
**Contact:** Development Lead
**Scope:** Code issues, test failures, minor compatibility problems
### Level 2 - Integration Issues (Response: 1 hour)
**Contact:** Development Lead + DevOps Engineer
**Scope:** Environment issues, deployment problems, system integration
### Level 3 - Business Impact (Response: 30 minutes)
**Contact:** Project Manager + Technical Director
**Scope:** Timeline delays, budget concerns, scope changes
### Level 4 - Critical Production (Response: 15 minutes)
**Contact:** CTO + Infrastructure Team
**Scope:** Production down, security breach, data corruption
---
## 📋 WEEKEND WORK PLAN
### Weekend 1 (Sep 14-15)
**Optional preparatory work:**
- Research PHP 8.4 new features
- Review competitor migration experiences
- Prepare additional test scenarios
### Weekend 2 (Sep 21-22)
**Critical development time:**
- Extended testing sessions
- Performance optimization
- Bug fixing marathon if needed
### Weekend 3 (Sep 28-29)
**Pre-deployment validation:**
- Final security review
- Complete system testing
- Production readiness validation
---
## 🎉 CELEBRATION MILESTONES
### Phase Completion Celebrations
- **Phase 1 Complete:** Team lunch - migration plan approved
- **Phase 3 Complete:** Team dinner - core migration finished
- **Production Deployment:** Company announcement - security enhanced
### Recognition Plan
- Individual recognition for team members exceeding expectations
- Company-wide communication highlighting security improvement
- Case study documentation for future migrations
---
## 📝 FINAL CHECKLIST
### Pre-Deployment Checklist (Day 17)
- [ ] All automated tests passing
- [ ] Manual testing complete
- [ ] Performance benchmarks improved
- [ ] Security audit passed
- [ ] Documentation updated
- [ ] Stakeholder approval obtained
- [ ] Rollback plan tested
- [ ] Monitoring configured
- [ ] Backup verified
- [ ] Team briefed on deployment
### Post-Deployment Checklist (Day 18)
- [ ] Production deployment successful
- [ ] All services responding
- [ ] Performance metrics within targets
- [ ] No critical errors in logs
- [ ] User acceptance confirmed
- [ ] Monitoring active
- [ ] Documentation updated
- [ ] Team debriefing completed
- [ ] Lessons learned documented
- [ ] Success metrics reported
---
**Timeline Owner:** System Development Agent
**Last Updated:** 2025-09-12
**Next Review:** 2025-09-13 (Start of Phase 1)
*This timeline is a living document and should be updated daily during the migration process.*